Casewatch Index
The
true source of uncertainty lies in the intentions of others!
from Game Theory
All
Casewatch Papers are in Adobe PDF Format.
Click on this Button to Download
a Free Reader
Casewatch publications are intended to be a topical report on recent cases in the construction, development and project industries. They are not intended to be a substitute for legal advice and no liability is accepted by Doyles Construction Lawyers or Mosaic Project Services Pty Ltd. |
Casewatch from Doyles Construction Lawyers |
||||||||||
|
Full List sorted by Topic: - Adjudication - Arbitration - Contract & Tort - |
|
Broad Construction v Vadasz
This case illustrates that where a report (or other evidence) is
relied upon in an adjudication response, an adjudicator may refuse to
consider the report if it was not properly included in the Payment
Schedule, consequently the failure to explain the full basis of
negating the payment claim can be fatal to a defence. [View Casewatch PDF]
Shorten v David Hurst
Constructions
The New South Wales Supreme Court examined the impact of
the
lack of proof available for the proper service of an adjudication
application and applied an ancient principal that no person could
profit by his own wrong. This case illustrates the need for careful
review of documents prior to service and also the need to ensure that
claims and application are properly served on all parties. [View Casewatch PDF]
Katherine v The CCD Group
The NSW Supreme Court has determined that in some
instances the
Courts may amend a portion of a determination under the Building and
Construction Industry Security of payments Act where an adjudicator has
determined an amount of interest under a construction contact which the
Court may construe as a penalty. [View Casewatch PDF]
Berem v Shaya Constructions
This case illustrates that the misdescription of parties
in a
payment claim may invalidate an adjudication based on such a claim as
no relevant construction contract exists to find jurisdiction for the
Adjudicator. [View Casewatch PDF]
Bezzina v Deemah
This case illustrates that careful submissions as to
jurisdiction are necessary to avoid challenge in higher Courts and may
have immediate application to contract managers and the way in which
they administer contracts, in order to avoid losing claims which may
otherwise succeed. [View
Casewatch PDF]
Rojo Building Pty Limited v
Jillcris Pty Limited
This case illustrates that a careful election between
alternative elections under the Security of Payment legislation avoids
an unfortunate loss of advantage to the Claimant. This judgement may
have immediate application to contract managers and the way in which
they administer contracts, in order to avoid losing rights which may
otherwise exist under the Security of Payments legislation. [View
Casewatch PDF]
Tsoukatos v Mustafa
This case illustrates that the Courts will examine and
weigh up
conflicting evidence in circumstances where service is challenged, and
that each respective party must be able to sufficiently discharge their
burden of proof to establish that service was either effectively
carried out or not received at all. This judgement may have immediate
application to parties to Security of payment disputes where personal
service is not practicable and there is potential for a dispute as to
the effectiveness of service. [View Casewatch PDF]
Halkat Electrical
v Holmwood Holdings
The Court of Appeal of New South Wales recently held
that an
Adjudicator who makes a determination as to the value of a
Payment Claim on inappropriate grounds does not perform their proper
function under the Act. This case
provides guidance to Adjudicators and parties in all states on the
preparation of claims [View Casewatch PDF]
Cant
Contracting v Casella.
The Supreme Court of Queensland recently held that
contractors
cannot rely on the Building and Construction Industry Payment Act 2004
to recover payment for work carried out without a licence in breach of
the Queensland Building Services Authority Act 1991. [View Casewatch PDF].
Inten
Constructions v Refine.
The Supreme Court of New South Wales recently confirmed
that the
requirement for natural justice under the Act must be considered in
light of the framework of the SOP Act, which does not give parties an
unlimited opportunity to make submissions. [View Casewatch PDF].
Queensland
v Epoca Constructions.
The Supreme Court of Queensland recently confirmed that
judicial review of Adjudicator’s decisions is available in
Queensland, but in reviewing a decision, the Court must be satisfied
that there is a clear error of law before it will set aside all or part
of the determination. [View Casewatch PDF]
Abigroup v Riverstreet.
The Supreme Court of Victoria recently confirmed its
position that recovery of the claimed amount as a debt due pursuant to
section 16(2)(a) of the Act is only possible where there is no real
question to be tried. [View Casewatch PDF]
JBK Engineering v Brick & Block.
The Supreme Court of New South Wales held recently that
the adjudicator’s task is to resolve the issues between the
parties, and found that the Adjudicator is only required to consider an
application based on the arguments raised by the parties, and the
reasons given by the Adjudicator demonstrated that he had considered
the progress claims and whether there was a reason for not allowing the
claim. [View Casewatch PDF]
Acclaim v Loewenthal.
The New South Wales District Court recently held that if
at the time of entering into the contract for residential building work
it is the intention of the owner to reside in the premises and this is
made clear to the contractor, then the Act will not apply to the
construction contract. [View Casewatch PDF]
Falgat v Equity (Appeal).
Given the strict timetable of the Act, parties should
ensure that Payment Claims and Payment Schedules are served carefully
and in accordance with the Act and other statutes to avoid later
disputes. Delivering documents to a companies registered officer
remains the most reliable way to ensure correct service. [View Casewatch PDF]
Bitannia v Parkline.
The Supreme Court recently held that contractors should
ensure that Payment Claims, and their service, are carefully executed
and are not misleading to ensure that their rights to judgment under
the Act are not affected. [View Casewatch PDF]
Baulderstone v Queensland Investment Corp.
The Court will consider whether a document is a Payment
Schedule by reference to the provisions of the Act. In doing so, the
Court tends to avoid being overly technical, but care should still be
taken when preparing a Payment Schedule to ensure that no doubt is left
as to whether the document is a Payment Schedule under the Act and that
the requirements of the Act are met. [View Casewatch PDF]
Fifty Property v O'Mara.
The question of whether a construction contract exists
between the parties to is a jurisdictional fact that is subject to
review by the Courts and parties should ensure that any contract is
clearly reduced to writing and executed to avoid later disputes. [View Casewatch PDF]
Wooding v Eastoe.
The Supreme Court recently held that it is for an
Adjudicator to decide who the parties to a construction contract are,
and an error in determining this question will not invalidate an
Adjudication Determination. [View
Casewatch PDF]
Procorp Civil Pty Ltd v Napoli Excavations and Contracting Pty Ltd
& Ors.
The time for raising issues with a Payment Claim is in a
Payment Schedule. Issues raised after this time may not receive
consideration by an Adjudicator, much less by the courts, and do not
require the Adjudicator to investigate by inviting further submissions.
[View Casewatch PDF]
Brookhollow Pty Ltd v R&R Consultants Pty Ltd & Anor
An Adjudicator should not to 'Rubber Stamp' Payment
Claims" but should consider all issues raised by the parties in an
Adjudication, as a failure to do so on a major issue may indicate a
lack of good faith, voiding the determination. [View Casewatch PDF]
De Martin & Gasparini v
State Concrete
The Supreme Court recently confirmed that an Adjudicator who wants to
decide a matter on which the parties agree on some other basis must
give the parties notice and an opportunity to respond to the point, or
the determination will be declared void. [View Casewatch PDF]
Pacific General v Soliman
The NSW Supreme Court held that the absence of relevant
material from Pacific does not entitle the Adjudicator to simply award
the amount of the claim without addressing its merits, which as a
minimum involve determining whether the construction work identified in
the Payment Claim has been carried out, and what is its value. To
simply rubber stamp the Claimant’s Payment Claim may result
in the Adjudication Determination being held void. [View Casewatch PDF]
Holmwood v Halkat
This case stands for the proposition that an Adjudicator must act
honestly, conscientiously and not capriciously, in determining an
Adjudication Application. Further, an Adjudicator’s failure
to evaluate a Payment Claim in the context of a payment Schedule and
the simple acceptance of only one party’s assessment may
demonstrate a failure to act in good faith. [View Casewatch PDF]
Energy Australia v Downer
This case stands for the proposition that an interlocutory
Adjudication Determination may not be valid if the claims contained
within the Payment Claim and Adjudication Application are of a
different nature. Further, notwithstanding the issue as to validity of
an Adjudication Determination, a Court may not interfere with the
payment process under the Act. [View Casewatch PDF]
Glen Eight v Home Building
This case stands for the proposition that an interlocutory
injunction is likely to be granted where an Adjudicator determines an
Adjudication Application in a manner which is not satisfactory or not
as he/she indicated is the proper way, his decision may be open to
attack. [View Casewatch PDF]
Air Dynamics v Durham
Where an Adjudication Certificate has been filed as a
judgment debt and paid, the Courts are unlikely to entertain any
further action that an Adjudication Determination is void, as the
purpose of the Act will be exhausted. [View Casewatch PDF]
Energetech v Sides
This case stands for the proposition that an Adjudicator
is entitled to finally determine a dispute as to whether a stage has
been reached in a contract for staged payments. [View Casewatch PDF]
Lucas v City of Sydney
This case confirms the proposition that the Act is a
strict liability scheme and that cross-claims for estoppel and
misleading and deceptive conduct, in the context of summary judgment,
are outside the scheme of the Act and unlikely to be entertained by the
Courts. [View Casewatch PDF]
Timwin v Façade
In determining an Adjudication Application, it is wise for
an Adjudicator to consider all submissions, even in the alternative,
because to not do so may leave an Adjudicator open to the decision that
he or she did not exercise his or her powers in good faith. [View
Casewatch PDF]
Taylor v Brick Dept
When a claimant is not insolvent, but may become insolvent
due to non payment of an adjudicated amount, the Respondent will not be
permitted an order of stay of execution of a judgment debt. [View Casewatch PDF]
Taylor v Brick
A payment claim sent by facsimile, whether within or
outside normal office hours on a business day, is regarded as being
served on that day (NSW only – Victoria has
different requirements). [View
Casewatch PDF]
Facade v Timwin
A stay to maintain a payment into court after a decision
that an Adjudicator’s Determination is void, is unlikely to
be granted merely by reason of the existence of a reasonable appeal. [View
Casewatch PDF]
Cooper v Veghelyi (Appeal)
This case confirms that a respondent is required to pay
into the court as security the unpaid portion of an award pending the
final determination of those proceedings. Further, this case highlights
the interim nature of the Act and that pursuant to section 32 of the
Act a respondent is entitled to an appropriate credit for the
Adjudicated Amount under the Contract. [View Casewatch PDF]
Tolfab
v Tie
A short form Payment Schedule which provides a clear
indication of the value of the work may be sufficient to allow a
Respondent to rely on reasons in its Adjudication Response if it puts
the Claimant on proper notice. Further, an Adjudicator is wise to
consider submissions in the alternative where practicable. [View
Casewatch PDF]
Minister
v Contrax - Appeal
Ay provision in a construction contract that diminishes, displaces or
delays a contractor’s entitlement to work may be void (and if
void presumably void for all purposes). Provisions subject to section
34 includes those relating to the determination of reference dates and
the calculation of the amount of progress payments even though the Act
expressly refers to such provisions.
[View Casewtch PDF]
Falgat
v Masterform
An Adjudication Determination is conclusive and res judicata is
applicable as the Adjudicator is akin to a judicial tribunal but that a
genuine dispute for the purposes of setting aside a statutory demand
can still exist.
[View Casewtch PDF]
Reiby
v Winterton
An Adjudication Determination is void if there is an apprehended bias
on the part of the Adjudicator and very high standards are expected by
the Court. The more concerning aspect is that a disgruntled party to a
determination under the Act may have an escape mechanism and avoid the
effect of a determination, in the event that the determination is
unfavourable, by making a request for a different Adjudicator on the
grounds of bias..
[View Casewtch PDF]
Co-ordinated
v Climatech
Claims
for delay damages can be the subject of Payment Claims under the Act,
if provided for by the terms of the particular Contract between the
parties but care still should be exercised when preparing the Payment
Claim. [View Casewtch PDF]
Schokman
v Xception
To
apply to adjudication when the Respondent fails to provide a payment
schedule, the Claimant must comply strictly with the statutory
timeframe. [View Casewtch PDF]
Coordinated
Constructions Co v J M Hargreaves & Ors
An
Adjudicators Determination is not void if it includes an incorrect
amount in the Adjudicated Amount [View Casewtch PDF]
TQM
v Dasein
Care
should be taken to ensure the Adjudication Application is actually
received [View
Casewtch PDF]
Review
of the BCISOP Act 2004
Review
of the Act in NSW - for amendments due in 2005 [View Casewatch PDF]
Estate
Property Holdings v Barclay Mowlem Construction
Some
work included in a payment claim must have been performed in the last
12 months [View
Casewatch PDF]
Brodyn v
Davenport (Appeal)
Judicial
review is not available to parties seeking relief from an erroneous
decision by an Adjudicator, except in very limited circumstances [View Casewatch PDF]
Digital
v QX Australia
An
interlocutory injunction may be granted where there is a dispute to the
validity or service of a payment claim [View Casewatch PDF]
Holdmark
Developers v GJ Formwork
Only
one final payment claim can be made at (or within 12 months of) the
termination of the contract or cessation of works [View
Casewatch PDF]
Minister
for Commerce v Contrax Plumbing & Ors
A
provision in a contract that delays or diminishes a contractors
entitlement to payment under the Act will be void [View Casewatch PDF]
Barclay
Mowlem v Tesrol Walsh Bay
To
'provide' a payment schedule means the process of delivery must be
initiated rather then actual receipt by the Claimant [View
Casewatch PDF]
Isis
Projects v Clarence Street
The
sufficiency of a payment claim depends on the conduct of the parties
and the history of the contract. The Court appears to be adopting a
liberal approach [View
Casewatch PDF]
Hawkins
Construction v Macs Industrial Pipework
The
Act applies to subcontracts entered into after the commencement date [View
Casewatch PDF]
Baulderstone
Hornibrook Pty Ltd v HBO DC Pty Ltd.
Summary
judgement provisions - various states [View
Casewatch PDF]
Bourke
Road Pty Ltd v Boxster Constructions Pty Ltd
A
creditors statutory demand for a debt due must not be submitted before
the expiry of the prescribed time for payment [View
Casewatch PDF]
John
Holland v Cardno MBK
The
Adjudication Application should not contain a new contractual basis or
new supporting documentation that was not included in the Payment Claim
[View
Casewatch PDF]
Transgrid
v Walter Construction Group 2004
The
Adjudicator is not bound by the Superintendents Certification [View Casewatch PDF]
Kembla
Coal Coke v Select Civil & Ors
A
claim for preparation costs, extension of time, delay and/or disruption
costs may be included in a payment claim [View
Casewatch PDF]
| Arbitration and other ADR |
Tryhaz
v Fielder
This case confirms the proposition that the Court will not
ordinarily interfere with the Referee’s Report and will not
ordinarily allow fresh evidence or submissions which could have been
made before the Referee. [View
Casewatch PDF]
Liverpol v Casbee
A party to an arbitration must exercise due diligence by
referring a dispute to arbitration without delay. However, for an
arbitration to be terminated a party must demonstrate that there has
been an inexcusable delay and a serious risk of prejudice, that is by
demonstrating the unavailability of witnesses and loss of documents or
other sources of information. [View Casewatch PDF]
Brecon
Builders v Ripa Steel
A breach of natural justice is likely to be committed where an
arbitrator decides a major part of a claim without giving the parties
fair opportunity to be heard [View
Casewatch PDF]
| Contract (including variations) & Tort |
Roluke v Lamaro
The New South Wales Supreme Court has recently examined the
heads of damages which a party may claim in respect of a diminution in
market value by reason of faulty workmanship and found that the Courts
may allow for an additional head of damage, namely, diminution in
market value to the structure where a nexus can be shown between the
defective workmanship and the reduced market value. [View
Casewatch PDF]
Dualcorp
v Remo
This case illustrates that
where a contract provides for a vague procedure for dispute resolution
(through a poorly drafted dispute resolution mechanism), the
Courts are not willing to allow an obscure and uncertain clause to
operate to exclude the jurisdiction of the Court, particularly in
circumstances where the clause on its interpretation is not reflective
of the parties’ apparent intentions. [View
Casewatch PDF]
Lumbers
v Cook
This case demonstrates the traditional position that in
normal
circumstances a subcontractor will have no claim against a property
owner for work done on the property. If the subcontractor wished to
have payment secured by the property owner a separate agreement or
special relationship would be required. [View
Casewatch PDF]
Multiplex
Constructions UK v Honeywell Control Systems
The English High Court has recently examined the
entitlement of
contractors to extensions of time with respect to the preventative
conduct of principals and the impact of that conduct on whether time is
at large. This case illustrates that careful contract administration is
necessary to avoid loss of entitlement to extension of time by a
contractor. [View
Casewatch PDF]
Perum
Building Construction v Tallenford
This case illustrates the importance of understanding the
terms
of the contract, clearly defining the nature of the contract, the scope
of work, and also underlines the importance of negotiation of the
contract terms ensuring that there are adequate provisions to
accommodate latent conditions, variations or misdescriptions.
[View
Casewatch PDF]
Sweeney
v Boylan Nominees
This case illustrates the importance of proper engagement
of
contractors in order that the principal is not vicariously liable for
the contractors default. The terms of engagement should
clarify
the varying indicia of the independent contractor, no control over way
in which the work was done, the contractor’s provision of
tools,
equipment, uniform, transport and payment for services rendered and
whether the contractor is to be presented as part of the
defendant’s organization. [View
Casewatch PDF]
Houghton
v Arms
This case illustrates the reach of the Fair-Trading
legislation
and the remedies available against individual employees for misleading
or deceptive conduct they are alleged to have performed as part of
their employment. It may have interesting application to officers of a
company who mislead others into trading with the company just prior to
administration or winding up. [View
Casewatch PDF]
Thiess
v Placer
This case stands for the proposition that good faith
involves
goodwill, co-operation and honesty between the parties and this extends
to the reasonableness and fairness in pricing. [View
Casewatch PDF]
Royal Botanic v South Sydney
The boundaries of the duty of good faith have yet to be
fully
determined but the Courts expect fairness and reasonableness from the
parties. [View Casewatch PDF]
John
Holland v Majorca
This case stands for the proposition that Architects do
not owe
a duty of care, and are not directly liable, to Builders under a JCC
Contract. [View Casewatch PDF]
Hughes v Air Services
This case stands for the proposition that the Courts
expect a
standard of fairness in contracts. A duty upon the parties of good
faith and fair dealing in the performance of contracts may be implied
and compliance with agreed tender process is covered by the
duty.
[View Casewatch PDF]
Far Horizons v McDonalds
This case stands for the proposition that an implied duty
of
good faith obliges each party to a contract to exercise the powers
conferred upon it in good faith or reasonably, and not capriciously or
for some extraneous purpose. [View Casewatch PDF]
Baulderstone v Qantas
This case stands for the proposition that a Superintendent
must
carefully consider and resolve a Contractor’s claim on its
merits
and must not be unfairly influenced by the Principal. Further, a
construction programme is likely to be considered by the Courts as a
statement of intention or expectation rather than a contractually
binding timeframe. [View Casewatch PDF]
Alcatel v Scarcella
This case stands for the proposition that a duty of good
faith,
both in performing obligations and exercising rights may, by
implication, be imposed upon parties as part of a contract. It extends
to prohibit unreasonably encouraging third parties to improve
obligations on the other contracting party for factual
advantage.
[View Casewatch PDF]
Kane v Sopov
This case stands for the proposition that where the
Superintendent does not act fairly and independently of the Principal
the Courts may determine that the Superintendent is not acting
fairly. [View Casewatch PDF]
Overlook v Foxtel
This case stands for the proposition that the duty of good
faith
is best regarded as an obligation not to act in bad faith. [View Casewatch PDF]
State of NSW v Coya
This case stands for the proposition that a Principal may be liable for
the Superintendent’s failure to properly consider and
properly
value variation claims but not to ensure he/she is always
correct. [View Casewatch PDF]
Renard v Minister for Public Works
This case stands for the proposition that reasonableness
may
overlap and be indistinguishable from good faith. Accordingly, in the
event of a Contractor’s challenge to the reasonableness of a
direction by a Principal, it is important to consider both the
reasonableness of the Principal’s actions and whether the
Principal was acting in good faith. [View Casewatch PDF]
Perini v Commonwealth
This case stands for the proposition that the Courts
usually
imply a term into the contract that the Superintendent will act, and
the Principal shall ensure that the Superintendent will act, in a fair,
unbiased and competent manner. [View Casewatch PDF]
Esso v Southern (Appeal)
This case confirms the proposition that a party may breach
its
duty of good faith if it acts unreasonably, capriciously, or in the
pursuit of an ulterior purpose. Further, a duty of good faith is a duty
of good faith is likely only to arise where a party is vulnerable or at
a disadvantage. [View Casewatch PDF]
Esso v Southern
This case stands for the proposition that the content of
the
duty of good faith encompasses two concepts; the prohibition of a party
from exercising a contractual power capriciously or for an extraneous
purpose, and the obligation to refrain from acting in 'bad faith'. [View
Casewatch PDF]
ABB Power v Chapple
This case confirms the proposition that for 'the
appropriate
enquiry' for the purposes of determining an entitlement to quantum
meruit is whether the recipient of the relevant services should have
objectively realised he would be expected to pay for them. [View Casewatch PDF]
Turner v Co-ordinated
This case confirms that for a building contract which
contains a
clause in the terms of clause 35.4, there is no room for the prevention
principle to operate because it is, in effect, excluded by the express
contractual provision. [View Casewatch PDF]
Pavey & Matthews v Paul
This case stands for the proposition that quantum meruit
is
based not on an implied contract, but on a claim to restitution or
unjust enrichment and arises from the acceptance of benefits accruing
to one party as a result of the work done by the other.
Further,
the obligation to pay fair and just compensation for a benefit which
has been accepted will only arise where such an agreement is
frustrated, avoided or unenforceable. [View Casewatch PDF]
Liebe v Molloy
This case stands for the proposition that if the work
claimed
for had been work required by the contract to be done, then the builder
could not recover for it, because he had not complied with the
contractual requirements. However, if the work was work which the
builder was not required to do by the contract (i.e. outside the
contract) then a builder may recover on the basis of quantum meruit if
the employer: (i) had actual knowledge of the extra works as they were
being done, (ii) knew that they were outside the contract, and (iii)
knew that the builder expected to be paid for them as extras. [View
Casewatch PDF]
Electronic v David Jones
This case stands for the proposition that if action is
required
to bring about the intended result, each party has the duty of
complying with the reasonable requests made by the other to ensure the
intended result is achieved. [View Casewatch PDF]
Dunlop v New Garage
The use of the words ‘penalty’ or
‘liquidated
damages’ does necessary mean that a clause is either a
‘penalty’ or a ‘liquidated
damages’ clause. The
Court will review the clause in light of the circumstances at the time
of entering into the Contract. [View Casewatch PDF]
Beckhaus v Brewarrina (Appeal)
Where the Contract works are defective, a Principal is
only
entitled to the difference between the costs incurred in rectifying the
defects and the amount it would have taken to complete the works under
the Contract. [View Casewatch PDF]
Wells v Army and Navy
If the Contract does not clearly provide for an extension
of
time as a result of the defaulting act of the Principal, the prevention
principle may be enlivened. [View Casewatch PDF]
Turner v Austotel
The prevention principle has no application to the JCCA
form of
contract due to the existence of an extension of time clause entitling
the Builder to an extension of time in respect of the preventative acts
by the Proprietor. Further, Builders who fail to comply with the notice
requirements for extensions of time may remain liable for liquidated
damages while losing their right to extension of time for the acts in
question. [View Casewatch PDF]
Trimis v Mina
This case confirms the proposition that where a principal
has
actual knowledge of the additional or extra works, knows that they are
outside the contract and knows that the builder is expecting to be paid
for the works as extras to the contract, then a builder may be entitled
to claim on a quantum meruit or restitutionary basis. [View
Casewatch PDF]
Peak v McKinney
This case stands for the proposition that a principal may
lose
the right to claim liquidated damages if some delay is due to the
principal’s defaults or the defaults of its employees or
agents
and the contract does not provide for an extension of time in that
event. [View Casewatch PDF]
Walter
v FTAC
The Trades Practices Act applies to everyone! [View
Casewtch PDF]
Stockland
v Coombs
When a professional is required to undertake additional work, a
percentage based remuneration may significantly under-recover the time
and costs incurred [View Casewtch PDF]
Roche
v Metro
A party may affirm a contract by continuing to exercise its rights
(work) under the contract after it is aware of a breach entitling it to
terminate the contract [View
Casewatch PDF]
Murphy
v Acumen
Practical Completion means completion for practical purposes! [View
Casewatch PDF]
Jennings
Constructions v Q H & M Birt
'Time bar' clauses create a condition precedent that must be met before
an entitlement to a claim can be made [View Casewatch PDF]
Rickard
Constructions & Anor v Rickard Hails & Moretti
& Ors
The cause of action in tort or contract can be assigned where there is
genuine commercial interest in the enforcement of the cause of action [View Casewatch PDF]
Tan
v Luxury
A construction contract will only constitute an 'entire contract' if
payment is conditional on the complete performance of the contract [View
Casewatch PDF]
|